Rapid Prototype Scheduling Lead Time of
1st New Sample submission of Pistons, Pin & Piston Rings |
|
|
|
|
| |
| Activities |
Period in weekdays |
| W1 |
W2 |
W3 |
W4 |
W5 |
W6 |
Design Product, Foundry mould / cores, M/C Shop Toolings using
ProE, Cad systems |
|
|
|
|
|
|
Material Procurement / Sub Supplier
part development |
|
|
|
|
|
|
Development, Manufacture of mould,
core, jig fixture using CNC /
Conventional machines using DRO |
|
|
|
|
|
|
Assembly of tooling and tune up
Machines |
|
|
|
|
|
|
Modification and approval o f
toolings, jigs & fixtures for 1 st batch
of samples, casting & machining |
|
|
|
|
|
|
Preparation of samples inspection
reports of Piston, Pin & Rings and
submission of samples |
|
|
|
|
|
|
|
|
|
|
|
|